|
Drilling
Since much will already be known in precise geological terms about
the lithology and structure of the rock mass, and it is generally
the goal only to locate and fill major conduits (as opposed to
treating microfissures), drilling should be conducted with the most
cost effective method available — provided always that it is
compatible with maintaining the security of overlying or adjacent
structures. This usually means using a direct circulation
down-the-hole hammer (Bruce, 2003) powered by compressed air, which
will help greatly in “cleaning out” clay from karstic features.
More recently, the use of sonic drilling techniques has proved
extremely advantageous. Holes should be drilled at least 150 mm in
diameter to permit the later installation of grouting-related
pipework. Depending on the rock mass structure, holes may be most
effectively inclined 10 to 15º off vertical. At least two rows of
holes are necessary, for geological and operational reasons, with
the holes in each row not spaced more than 3 meters apart on
centers. It is essential to log carefully the drilling conditions
encountered in each hole, so that a simplified geological profile
can be established, identifying, as a minimum, the locations and
extents of the following:
• overburden, • hard massive rock, • fissured rock,
• very weathered rock, • clay infilled karst, and • voided
karst.
During the drilling of each hole, the exit point of the flow, if
accessible, must be continuously monitored to determine if the
conduit has been influenced: flow volume, color changes, and the
presence of compressed air (if used as drill flush) are critical
observations. Any interconnections between holes must be accurately
recorded (depth and distance) since they will be vital to consider
in designing the grouting operation.
Grouting materials
In the case of fast, large volume flows in very large conduits,
conventional “slurry” grouts — also known as high mobility grouts (HMG)
— will simply be washed away. Even thoughtfully formulated HMGs fail
to perform in these circumstances, and even have the potential to
cause an environmental problem downstream of the curtain [High
Mobility Grouts: HMG (Chuaqui and Bruce, 2003)].
Similarly, the potential benefits of highly sophisticated — and
expensive — chemical grouts (Bruce et al., 1997) are rarely
exploitable since they lack the short-term gelling and strength
characteristics to mechanically resist the hydrodynamic forces in
the conduit.
In contrast, I’ve experienced success using either low mobility
grouts (LMG) [Cadden et al., 2000] in lower head, low-velocity
conditions, and hot bitumen (together with HMG and LMG) in
particularly adverse conditions. Various additives and admixtures,
including accelerators, antiwashout agents, viscosifiers, and
polypropylene fibers are used by better contractors to tailor both
LMG and HMG grout combinations to the precise project requirements.
Grout injection and sequencing
It is common to find all, or most, of the flow channeled into one or a
small number of well defined conduits, although very soft, potentially
erodible, or fissured rock conditions may still exist in the surrounding
bedrock. The basic principle is to allow the flow to continue in these
conduits, while treatment continues of the rock mass (through which
water is not yet flowing) around the conduits. Depending on the nature
of the rock mass, this preemptive treatment can be conducted by
conventional, open-hole staging methods, or by the MPSP system (Bruce
and Gallevresi, 1988) — both of which use families of HMG — or by using
LMG in upstage, end-of-casing applications. Again, observation of the
flow outlet point is essential at all times, together with an ongoing
assessment of any changes to piezometers and other instrument readings.
Typically, little benefit — in terms of flow or pressure reduction — is
found at this time, even though it is absolutely essential to conduct
this work at this juncture (i.e., at a time when the water flow rate in
this part of the final grout curtain is minimal).
The last, and most critical and dramatic phase of the grouting program
is to then put the plug in the conduit, given that the surrounding rock
mass has now been protected against the danger of internal erosion when
the curtain is functioning. When dealing with flows of 40,000 gpm or
more and head differentials of more than 100 ft., cement-based grouts —
even those of high rheology and accelerated hydration — cannot be relied
upon to resist the hydrodynamic situation in the conduit. In such
extreme conditions, the use of hot bitumen, in conjunction with the
simultaneous and adjacent injection of HMG and/or LMG, has proved to be
a most reliable solution.
Bitumen has been used in projects around the world for decades, but it
is only within the last few years that full engineering value has been
extracted from its extraordinary potential. In short, the hot bitumen
encounters the flow which quickly removes the heat from the material
(injected at temperatures of 200ºC and higher). The material begins to
gel and congeal and thus, when pumped at sufficiently high rates, will
begin to overwhelm the flow in the conduit. The simultaneous upstream
injection of LMG or HMG causes these materials to be pushed against the
cooling, but still relatively hot bitumen mass, leading to a “flash set”
of the cement-based grouts in the conduit. This multi-material plug
continues to form as injection continues. Eventually, the conduit is
(temporarily) plugged with the gradually cooling (and shrinking) bitumen
plug. At this point, further rapid injection of HMG and LMG is continued
upstream of this temporary plug to create the final plug which should
eventually resist the hydraulic gradient applied to the temporary plug.
Failure to conduct sufficient HMG and LMG grouting at this time will
simply ensure the ultimate failure of the operation because the
temporary bitumen plug will continue to cool and shrink and so permit
the water to exploit the growing gap between the conduit boundary and
the bitumen. The plugging operation must be continued without
interruption until completion: unless bitumen is pumped continuously
down through the specially installed pipework at high temperatures, the
system will freeze prematurely, and the conduit will not be accessed.
The organization and management of the plugging operation is an exercise
in detail and logic and must involve the skills, input, and cooperation
of all parties. Clear field leadership is essential.
Recent case studies
West Virginia (Bruce et al., 2001) — An inflow of about 40,000
gpm suddenly developed into the floor of this fully operational
quarry, originating in a river about 1,500 ft. away. The head
differential was over 160 ft. Remediation had to be undertaken
since:
a) the quarry was an integral part of a major commercial
organization, having long term aggregate supply contracts to
satisfy; and
b) it would have been prohibitively expensive to pump on an ongoing
basis.
Desk studies were supplemented by programs of geophysical testing
(fracture trace analysis, EM surveys, and dipole-dipole) and
exploratory drilling. These holes were sampled for water chemistry,
pH, and temperature. The result was that the likely flow path was
identified, being — at its most intense — more than 50 ft. wide and
at two elevations (60 to 100 ft. down; and as deep as 200 ft.).
However, other karstic features, as yet not transmitting water, were
found over a far larger lateral and vertical extent. Following an
assessment of the viability of other options, a two-line grout
curtain was designed, about 1,200 ft. long, 230 ft. deep, and within
70 ft. of the river bank.
The work was conducted in several successive phases, each driven by
the analysis of the results of its predecessor. Locally, the curtain
was thickened or regrouted in response to the developing picture.
Success, in this case the reduction to a total inflow of about 7,000
gpm, was achieved — temporarily — on several occasions, only for the
integrity of the curtain to be compromised as a result of clay
filled karsts being blown out under rising gradients. Eventually,
however, success was achieved — inflow from the river was virtually
eliminated under a differential head of 140 ft. This project
required the injection of 8,400 cu. yd. of HMG, 2,140 cu. yd. of LMG,
and 6,100 cu. yd. of hot bitumen.
Missouri — A virtually identical problem was encountered in Missouri
three years after the West Virginia project. The same generic
approach to assessing the problem and designing and executing the
solution was adopted. Extensive use was made of electrical
resistivity and spontaneous potential geophysical exploration, dye
testing, aerial photography, and piezometric observations. The
velocity of the underground flow reached about 80 feet per minute.
In this case, the river created a maximum differential head of about
300 ft. on the base of the quarry, and the maximum recorded inflow
was about 30,000 gpm.
A multi-row, 260-ft.-long grout curtain was constructed to a maximum
depth of 350 ft. Intensive treatment of the incipient karstic
features was first and systematically conducted to improve the
ground around and under the location of the main conduit, found to
be about 230 to 280 ft. down and 60 ft. wide. The major difference
in the geology with the previous case was that the boundaries of the
conduit were found to be relatively competent. As a consequence, the
actual formation of the final plug — although it took several weeks
to plan, organize, and prepare — took barely 48 hours. The result
was total elimination of the flow and full restoration of
piezometric levels upstream of the curtain. The overall curtain
involved injection into about 77 holes of approximately 2,150 cu.
yd. of LMG, 3,700 cu. yd. of HMG, and 215 cu. yd. of hot bitumen.
The relatively competent nature of the bedrock around the conduit
permitted straightforward stage grouting procedures to be used with
the HMG in the pretreatment phase of the operation, as opposed to
the MPSP system necessary for the similar phase of treatment in the
much less competent rock mass found in the West Virginia project.
Conclusion
Space restrictions prevent full descriptions being given of the
two case histories summarized above. The reader should be cautioned
from believing that these projects were anything other than
extremely stressful for all the participants. They demanded the
highest levels of technology, administrative, engineering, and
management skills, as well as attention to detail.
There is an old adage that “you find out about people in adversity.”
The development of a sudden and major flow into or under a major
engineering structure founded on or in karstic limestone presents
serious adversity in various forms to all concerned.
It is hoped that this article will in general provide comfort,
confidence, and guidance to those who are faced with such events. In
particular, it may form the basis for contingency plans or protocols
that could be developed (and hopefully left on the shelf) by
managers of major facilities founded in karstic limestone terrain.
References
Bruce, D.A. (2003). “The Basics of Drilling for Specialty
Geotechnical Construction Processes.” Grouting and Ground Treatment,
Proceedings of the Third International Conference, Geotechnical
Special Publication No. 120, Ed. L.F. Johnsen, D.A. Bruce, and M.J.
Byle, American Society of Civil Engineers, pp. 752-771.
Bruce, D.A. and Gallavresi, F. (1988). “The MPSP System: A New
Method of Grouting Difficult Rock Formations.” Geotechnical Aspects
of Karst Terrains, ASCE Geotechnical Special Publication No. 14,
Presented at ASCE National Convention, Nashville, Tenn. May 10-11,
pp. 97-114.
Bruce, D.A., W.G. Smoak, and C.C. Gause. (1997). “Seepage Control:
A Review of Grouts for Existing Dams,” Proceedings of the
Association of State Dam Safety Officials, 14th Annual Conference,
Pittsburgh, Pa., Sept. 7-10, Compact Disc.
Cadden, A.W., D.A. Bruce, and R.P. Traylor. (2000). “The Value of
Limited Mobility Grouts in Dam Remediation.” Association of State
Dam Safety Officials Annual Meeting.
Bruce, D.A., R.P. Traylor, and J. Lolcama. (2001). “The Sealing of
a Massive Water Flow through Karstic Limestone.” Foundations and
Ground Improvement, Proceedings of a Specialty Conference, American
Society of Civil Engineers, Blacksburg, Va., June 9-13, Geotechnical
Special Publication No. 113, pp. 160-174.
Chuaqui, M. and D.A. Bruce. (2003). “Mix Design and Quality
Control Procedures for High Mobility Cement Based Grouts.” Grouting
and Ground Treatment, Proceedings of the Third International
Conference, Geotechnical Special Publication No. 120, Ed. L.F.
Johnsen, D.A. Bruce, and M.J. Byle, American Society of Civil
Engineers, pp. 1153-1168. |
Donald A. Bruce, Ph.D. is
president of Venetia, Pa.-based Geosystems, L.P.
He can be reached at 724-942-0570.
(part 1 of article click here)
|