November 2001

Operations

Pit Sense--Reserve Estimation: Getting Figures Truly Written in Stone

Gravitas Superabit, Part 2--Selecting a Roof Bolting System

Success in the Field--Fox River Implements Metso Turnkey Operation

Maintenance Matters--Battery Battles

Winter Battery Storage Tips

Pit Sense

Reserve Estimation: Getting Figures Truly Written in Stone

By Larry Bolling, P.G.

A basic goal of every mine plan is to maximize mineable reserves. Every quarry manager or pit supervisor probably has some idea of the quantity of reserves remaining at their site, but exactly what is this idea based on?
In general, reserves consist of that portion of available geologic resources that can be economically extracted. Physical features such as landforms, geologic features, groundwater levels and bodies of surface water place obvious limits on mining existing resources. Ownership and permit constraints further limit exploitable reserves. Even after accounting for all these issues, the reserves must still be of acceptable quality to meet applicable product specifications. All these factors conspire to whittle away at the volume of reserves that are actually mineable and worth going after, underscoring the need to wisely manage those reserves that remain.
Performing a reserve estimate can be as simple as measuring several areas on a scaled map and assuming an average thickness of material, or as complicated as computer modeling of rock type and quality data for every 50 ft. block of material on a property. In practice, most estimates fall somewhere in between these two extremes. The purpose of the reserve estimate and the amount of information that is available generally determine the scale of the effort expended on the project.
The reasons that compel companies to perform a detailed reserve estimate are varied. Sale or purchase of a mining operation or valuation of a mining property can trigger a reserve study. Questions regarding reserve abandonment or sterilization as a result of overburden disposal, processing plant relocations and expansions, stream relocations or difficult mining areas can only be answered accurately through detailed analysis. If quality of the rock is an issue, a blending plan might be the answer to extending the operating life of a quarry. Even customers can precipitate an analysis by demanding proof of the existence and quality of reserves before committing to long-term purchase agreements.
The first step in estimating reserves is to gather together all the information that is available on your site, the geologic resource you are mining and pertinent mining regulations. This might include deed and lease documents; mining permits; regional or municipal planning and zoning documents; local mining ordinances; geologic reports from various federal, state and local sources; water well data; drilling records; and any testing data available. Organizing and becoming familiar with this information will identify all the existing constraints on mining, paving the way for a realistic reserve estimate.
Incidentally, this stage presents a good opportunity to document and preserve site information for a mining operation. For many operators, just gathering this information is a major project. The reports, test data, and drill logs that might be available represent a large investment of your company’s time and money. Organizing and preserving this information ensures that the greatest benefit is derived from the investment. There are a number of ways to consolidate this information, both in hard copy and digitally, that can make it easily accessible and available to anyone who might require it.
Once the available information is compiled and organized, it is possible to identify the gaps in the data. The next task is to identify appropriate methods to fill in those gaps. Depending on the scale of the information required, these methods might include aerial photography and mapping, geophysical studies, drilling test holes, geologic field studies or digging test pits. Obtaining information to complete a database is the most expensive part of the entire process. Generally, the level of cost is inversely proportional to the scale of the information required.
If quality analysis is required, a sampling and testing program must be developed. The program should provide enough information to augment whatever data are already available to satisfy the goal of the reserve estimate. For example, is it sufficient to confirm the existence of half a million tons of high-quality material, or is the goal to provide a general idea of the quality available on the entire site? Detailed quality analysis can get very expensive, due to drilling and testing costs. Concentrate on the material properties that are critical to your operation, but don’t ignore other potential problems. Running an occasional sample through a complete battery of tests can provide a baseline of data for future sampling programs and might alert an operator of potential problems that could be addressed before becoming critical.
Sometimes, less costly methods can be used to supplement or confirm information. For example, test pits completed using an excavator available on site might be an acceptable alternative to auger holes in overburden or sand and gravel studies. Air rotary drill holes might produce acceptable material for testing at a fraction of the cost of diamond core holes. Or, maybe soundness loss results correlate to another characteristic of the rock in question, such as absorption. Just be careful not to consider results from substitute methods as reliable as those obtained using the best method available.
The distance between data points depends on the required degree of accuracy of the study as well as the geologic setting. The end result is always a compromise between cost and confidence. Seek the input of a qualified person who is familiar with the formations under investigation, as well as the quality issues faced by producers, to help develop an appropriate sampling and testing program.
After sufficient information is available, analysis can begin. Reserve quantities can be computed based on location, quality and scheduled availability. Computer modeling, performed properly, can provide a wealth of information in formats from spreadsheets to colored maps, tailored to the operators’ specific needs. Keep in mind the standard computer adage: Garbage in, garbage out. Modeling methods must be appropriate for the data being analyzed and must respect all constraints you worked so hard to identify at the beginning of the process.
The end result of this effort is to provide you with the information to satisfy your original goal. Weeks of work might even be reduced to a single number: the tons of material available for mining at a specific site. Take the necessary steps to develop an accurate reserve estimate for your operation, and it can result in figures that truly are written in stone. 

Larry Bolling, P.G., is a geologist with the Industry & Environment Group of Morris & Ritchie Associates, Inc.


Gravitas Superabit, Part 2—Selecting a Roof Bolting System

By Jack Parker

Part 1 of this series was a general discussion of roof bolting in stone mines. In this part, we go on to actually selecting a system.
The first question to ask and answer is this: Do we really need roof bolts? If the need is not obvious, but an authority decrees that “This roof shalt thou bolt,” it would make sense to ask him to explain why, and to explain it in simple terms. If the explanation is too technical, it is suspect.
If roof conditions need help, then see if they can be put right in some other way, perhaps by selecting a different roof horizon or by changing orientation of the mine openings. You look for the opportunities.
If the explanation is credible and if there are no acceptable alternatives, then go forward with some reasonable design approach.

CHOICE OF BOLTS

Here are some generalizations to consider. Not everybody will agree with all of them. You figure it out.
The first choice is often between mechanical and resin anchorage.
If the function of the bolts is cosmetic, or maybe to suspend occasional slabs, or to offer some insurance for a short period of time—then mechanical anchors may suffice. Potential problems are that the serrations on the shell of the anchor gradually creep into the rock, allowing the bolt to lose tension; that moisture will cause the bolts to rust; and that weathering of the rock around the bearing plate will cause the bolt to become completely ineffective. On the other hand, they should cost less, and they can be installed without special roof bolting equipment.
Resin/rebars overcome most of the difficulties. Anchorage is distributed over the grouted length, resin protects against corrosion and even if the rock weathers away from the bearing plate, the resin/rebar will continue to hold the rock together. A problem for some folks is that a smaller hole must be used (to ensure mixing of resin and catalyst) and the rebar must be thrust and spun into the hole to do the mixing. For long-term support, the resin/rebar bolt will almost certainly be a better choice.
Cement-grouted bars will perform the same function, but they are most often used where a large number of holes are drilled. The bolts are then installed using a batch process for the cement. Resin comes in sausages and sets up quicker—so the operator gets roof support as he goes, always working under supported ground.

LENGTH, STRENGTH AND SPACING

The textbooks and much of the literature will tell you that you can “build” beams by binding the layers or chunks together but, in my opinion, the end result we, in mining, look for is to prevent the rocks falling—which, when you work through it, boils down to suspending the potential loose rock from some stable zone.
I would try to define the zone to be suspended by looking at all of the roof falls I could find. They might, for example, include 3 ft. of geologically thin-bedded, blast-damaged shaly limestone, stopping at a more massive bed.
In this example, the spacing would probably depend on what “looks right”, i.e., close enough to ensure that few chunks would fall from between bolts. If rock were likely to fall from between bolts, we would probably add wire mesh or steel mats to contain it.
Every square foot of that roof would potentially be loaded by 3 cu. ft. of rock. Limestone weighs around 1 ton per 12-1/2 cu. ft., so, if we thought that 5-ft. centers would be about right, each bolt would have to suspend 25 sq. ft. weighing 25 x 3 / 12.5 = 6 tons—which could be handled easily by standard 5/8-in. mechanical bolts or standard 3/4-in. rebars (but check the specs on all available bolts).
Next comes the question of bolt length, i.e., where is the stable zone?
To determine bolt length, we now try to define the stable zone from which we can suspend the potential loose rock.
A stable arch? Most falls of roof, even in sand, probably work their way up to an arch shape, which would be more-or-less stable. There are several ways to explain that.

In almost all mining situations, there is some horizontal compressive stress in the rock mass—and that works to hold the roof rocks in place. But if that stress is too low, or if the room is too wide, or if the rock itself is weak—then the roof sags into the mine opening and a zone of tension develops in the immediate roof. That is the zone that wants to fall out. But the horizontal stresses now arch up and over the mine opening, creating a zone of increased compression—hence a more stable zone.
The shape of that zone is controlled largely by the ratio of horizontal stress to vertical stress. Within moderate limits, a high vertical stress forms a high elliptical arch and a high horizontal stress forms a low elliptical arch, as in these sketches (Figure 1).
We could recognize local conditions by examining all of the falls of roof, and/or by drilling observation holes in the roof and examining them to define the uppermost fractures and separations. We could use a borescope to find them, or going low-tech, we could use a homemade scratcher. Remember the scratcher? It is a length of 3/4-in. steel conduit, the last inch or so flattened, bent over at right angles, then ground or filed to a sharp, thin point. You can mark it in inches, or centimeters if you intend to publish the results in Mining Engineering. You shove it up the hole, then drag it down slowly, “feeling” the walls of the hole. You should be able to sense smooth rock, rubbly zones and separations. If you think that you have detected a separation, rotate the tool to make sure that the crack is present all around—not just a chip off the wall. Jiggle the tool up and down to get a feel for the width of the separation. Note the depths to all interesting features. Get sophisticated if you wish and bear down on the rock and listen to the sound effects: a high blackboard-like screech comes from fine-grained hard rock, wet shale sounds like mud and intermediate noises come from intermediate conditions. The tool was originally called a cracksnagger (Figure 2).

A somewhat similar situation may exist where the rock is fairly massive, behaving something like a beam. As the textbook would point out, the underside of a working beam is in tension, the topside is in compression and somewhere between top and bottom is the “neutral axis,” an imaginary line along which the beam is neither in compression nor in tension. We would want our bolts to be anchored above that neutral axis (Figure 3).
Even in blocky ground there is some hope that a “beam” will be formed as the blocks key together in compression at their tops, in what is called a “voussoir arch”—the sort of thing you used to see in old stone bridges. In this situation, the lower tensile zone would again be suspended from the upper compressed zone (Figure 4).

If we stretch that idea a bit, we come close to the textbook idea of beam building. Look at it this way: if a beam is too thin it will sag and “buckle through” because the neutral axis is above the top of the beam, but if we can pin several such beams together, to form a composite beam, then the neutral axis may be within the composite beam—and it may survive. But perhaps it is not truly a beam structure, because of the natural cracks and weaknesses in most rocks, but a grouping of thicker blocks, can now form a thicker voussoir arch, which may be stable (Figure 5).
If, after doing your best, you find the roof on the floor with the bolts sticking up like a pincushion, then the odds are that the bolts were not long enough (Figure 6).
And if, even after diagnosing and correcting pre-existing problems, not all of which have been mentioned—like gas or water pressure in the roof, and others I am leaving for you to work out—there may be special situations which require special treatment.

A recent example occurred in part of a mine where the roof was cut by two sets of joints, parallel in trend but dipping in opposite directions, to form long, heavy wedges of rock in no way bonded to each other (Figure 7).
The first step would be to orient the mine openings so that the great majority would cross these joints at right angles (to minimize the length of the wedges), to make those openings that are parallel to the joints as narrow as possible and to stagger the intersections. Then we work on the roof bolting—and we have to bind those wedges in place as early as possible with steel straps running from bolt to bolt across the joints. And we would have to sketch some cross-sections of the geology and the roof falls to determine bolt length (Figure 8).
OK, so we have found a stable zone in which to anchor, now we have to get the anchorage. The general idea is that each bolt will have to support our calculated load, with a bit to spare.

PULL TESTS

The bolt manufacturers and the other experts will probably recommend pull tests—to promote the value of their wares, but beware of pull tests because they can mislead. Let me give examples.
This is how they are supposed to work: a bolt is installed and a hydraulic jack is affixed. Tension is applied and, at fixed intervals, say every ton of load; the movement of the head of the bolt is measured, usually to the nearest thousandth of an inch. Normally it takes a ton or two to settle down, and then a fairly regular change is seen with each ton of additional load, until something different happens, and the trend of the graph would change. Maybe the steel starts to stretch, maybe the anchor starts to slip, or maybe the hydraulics are leaking. I have seen the hydraulic jack bottom out and the tester said, “Wow!” (or something like that): “That anchor’s not budging!”
The operator may choose to continue to add load, but usually not to complete bolt failure because that may be sudden and may do damage. News item: “Sales rep observing pull tests harpooned by 6 ft. roof bolt. Grade 75 bolt broke at 16 tons. Brittle fracture. Combination anchor and bolt meet specifications. System approved. Next-of-kin to be informed.”
If he, the tester that is, does not choose to continue the test to failure, then it is a good idea to back off the pressure ton by ton, noting the displacements again—to find out how much permanent displacement there has been. But beware! Results may not be what they appear to be.
With mechanical anchors, the test result is for short-term anchorage, but as hours, days, months and years pass, it is not unlikely that they will become loose—because most of the load is borne on a few sharp teeth digging into the walls of the bolt hole. You may want to check performance over a longer time-span, perhaps with a simple torque wrench. Adding a slug of resin to mechanical anchorage should improve long-term performance.

The performance of resin/rebars in pull tests may also be misleading, since they are commonly performed on a fully-grouted bar, maybe 4 or 6 ft. long. That means that several feet of anchorage is available to resist the pull, whereas that may not be the case in real life (Figure 9).
In Figure 9, a mass of rock about 4 ft. thick appears to be suspended from a strong upper beam by 6-ft. rebars—so stability actually depends on the anchorage only in the top 2 ft. of rebar—and we can discount the top-most few inches of that because there the resin is not likely to harden.
It is more meaningful to run tests on short lengths of anchorage, say 10 in., 20 in., 30 in. and so on, or to test anchorage on the most probable working length (the top 2 ft. in the sketch).
And of course the resin manufacturers’ instructions for installation must be followed.
The same caution should accompany tests of the various “friction anchorages,” which are usually performed on full-length samples, whereas the working anchorage may not be full-length.
A typical resin/rebar in a decent limestone should provide about one ton of anchorage per inch of good resin, i.e., a foot of good resin should offer about 10 tons of resistance (but we should run the tests). See Figure 10.
Note that resin anchorage, properly installed, may still fail in two ways:

  • If the rock is relatively soft, and/or wet and/or smoothly drilled—then the failure is likely to be in the rock immediately adjacent to the resin—the system will slip as the rock shears. After a fall of roof, you will probably see rebars in the rockpile still encased in a smooth covering of resin.
  • If the rock is strong—stronger than the resin (which is mostly ground limestone), then excessive load will crush the resin under the deformations on the rebar, beginning at the collar of the hole (or where the load is initially applied) and working its way up the length of the bolt. After a fall of roof, you will probably see pulverized resin on exposed rebars. A remedy might be to expose more resin to the load by using rebar of larger diameter or rebar with larger deformations.

There will probably be heated debate on the question of tensioning resin/rebars. I am reasonably sure that it is not necessary and often not to be desired. First—only a few thousandths of an inch of rock movement is needed to tension the rebar, which means that it will probably happen naturally. Then there are the problems which accompany pretensioning—too much torque and partially twisted-off nuts or bolt heads.
Another factor not generally recognized is that immediately after excavation of a mine, opening the rocks typically relieve some of the stress in them by moving a little into the opening, much as a pane of window glass might be bowed after installation (you can see wavy reflections in the glass). Obviously it would be unwise to push on the glass to straighten it, and likewise it is unwise to try to force rocks back into their original overstressed position. Just snug them up! As a matter of fact, it is sometimes best to design bolting systems that will yield a little, instead of breaking.
But that is a special situation. You may have seen it in evaporite mines—salt, potash, etc.—where roof beams separate and bow downward several inches (I’ve seen 18 in. of separation) without breaking. In some of my photos, those rocks remind me of wet cardboard.
Somewhat reluctantly, let us close now—not having covered the topic completely—with a summary of the most important steps.

SUMMARY

1. Do we really need bolts? Plenty of mines manage without them. Some spot bolt in special circumstances. Some install cosmetic bolts. Some use an “approved” pattern throughout the mine to avoid confusion, which might come if choices were allowed.
2. Are there ways to make bolts unnecessary? Think about it!
3. Can we mine a greater thickness to help justify the cost of bolting? Say 50 ft. high instead of 25 ft. to halve the cost per ton…
4. Choose the system from mechanical anchorage or grouted rebars, to suit local conditions—hard rock or soft rock, wet or dry etc.
5. Determine where anchorage should be to form a stable structure. That will determine the length of the bolts.
6. Figure out a suitable spacing, usually to prevent falls from between bolts and plates. Add straps or mesh if necessary.
7. Figure the load per bolt, from number of cubic feet of rock to be suspended from the anchorage, at about 12-1/2 cu. ft. per ton.
8. Select the bolt strength to suspend that load. Civil engineers are likely to work with the yield strength of the bolt; miners are more likely to work with the ultimate strength, knowing that bolts are usually 10 to 15 percent stronger than the manufacturer specifies.
9. Test the system selected, in a small, out-of-the-way place if possible. Refine if necessary. And never stop thinking. Until we get that anti-gravity paint on the market we’ll always be looking for better ways to control the roof.

To close on a Scriptural note, we have an appropriate selection from John 21, v. 3:
Simon Peter saith unto them “I go a-fishing.”
Everybody has to believe in something; I believe I’ll go fishing too. And if perchance we meet at The Gates, we’ll have a lot of stories to tell. Peter will make allowances for fish stories, which are, by definition, not lies.

Jack Parker is the owner of Jack Parker and Associates. In reality, Parker has downsized, and the “Associates” are Jack’s wife, Levinia, and her small dog, Dulcie.


Success in the Field

Fox River Implements Metso Turnkey Operation

Rock from Fox Riveršs new crusher (center of photo) is conveyed
to an 8-by-20 finishing screen and then deposited to be picked
up by a wheel loader.

About 2.0 million tons of rock are now available to Fox River Stone
customers annually, an increase of 36 percent over last year.

Located 40 miles west of Chicago in the Fox River Valley, Fox River Stone Company was at its capacity to provide aggregates to its customers due to the increase in new-housing and road construction in the area.
The quarry had adequate reserves, but needed to increase capacity and lower operating costs. Consequently, in the spring of 1999, Rein, Schultz & Dahl, Fox River Stone’s parent company, decided to invest in a state-of-the-art aggregates processing facility.
The company developed design criteria and sent out bid packages. The packages asked for bids for a plant that would provide a 50-percent increase in rock produced per hour and rock that would meet Illinois DOT specifications. The call for bids asked for a turnkey delivery that included everything from planning the production flow to installing the crushing plants.
When Metso Minerals received the request for bid from Fox River Stone, Jack Lange, its manager of systems application and design, and his team of 11 people developed a plan.
The Metso Minerals team created a computerized flow chart of the plant and determined the optimum production capability for each required product. The plant was then analyzed to ensure complete flexibility for producing new products, re-screening of products and operating at reduced production during maintenance periods.
The previous machinery produced 500 tph; the new Nordberg primary crusher produces 750 tons per hour with a maximum capability of producing 850 tons per hour, according to the company. Three 50-ton trucks make about 21 trips per hour between the quarry and crusher.
Yearly production capacity will increase and provide customers the opportunity to purchase up to 2.0 million tons a year, which is a 36-percent increase over previous years.
Construction on the new plants began in November 1999, while the quarry was still in operation. All footings were poured and support materials were put into place before the plant was shut down to install the new crushers and update the conveyors.
Metso Minerals provided an onsite project manager during the construction of the plants, and even though all of the mechanical and automated systems were tested at the company’s Milwaukee facility prior to installation, Metso Minerals sent technicians to the quarry on a regular basis to ensure everything was working properly.
An important part of the project was the development of a computerized operating system tied together with a fiber-optic cable, allowing the primary plant to be controlled by the secondary-plant operator. Metso Minerals worked with Fox River Stone and an integrator to install a system that became the eyes for the plant operator.
The primary crusher has two television cameras that are monitored by the plant operator in a control tower at the secondary crushing plant. Previously, the primary crusher had an operator in a control room watching the plant 100 percent of the time.
In addition to monitoring the equipment, the automated system tracks much of the statistical data of the quarry. Reports can be produced showing the number of hours the crushers have run, how much down-time has occurred, tons of each product produced per day, total primary and secondary plant tonnage per day and other statistical data that enables plant managers to make effective plant-management decisions.
The automated system provides the operator with data, which he uses to schedule repair work and preventive maintenance. Each crusher, screen and the 4,000 ft. of conveyer belts are monitored by sensors that route information through a programmable logic computer which is interfaced with a desktop computer. This computer has custom-designed graphics that show the operator the product flow through the primary and secondary plants. The operator knows which pieces of equipment are running and their operating condition.
The sensors allow the plant operator to know what is going on with the machinery in real time. If a problem occurs somewhere in the system, the computer shuts down the plant sequentially. This prevents a pile-up of rock, unnecessary clean-up and serious damage to equipment.
Sensors also allow plant operators to pinpoint problems and eliminate guess work. And, in the event the automated system goes down, there is a backup manual system at the primary and secondary control towers.
Not only is the machinery more productive, but the automated system also allows employees to concentrate on the little things, like clean-up, lubrication and preventive-maintenance checks that make the quarry run smoothly. Mike Lacke, vice president of operations for Rein, Schultz & Dahl, said no employees were let go as a result of all this automation.
“We’re going to be able to increase production by 36 percent over last year and keep the plant’s manpower at the same level,” he said. “We now have a computer system that does the mundane duties, allowing employees to be more productive with their time.
“Our employees have worked hard to learn how to operate and maintain the new plant, which has contributed to the success of this project,” said Lacke.
During construction and onsite testing, and after the plant was up and running, Metso Minerals personnel were onsite to ensure the plant was running smoothly and construction was on schedule.
Fox River Stone employees also attended training sessions at Metso Minerals to learn about the equipment and received hands-on training on maintaining and repairing the plants. They also were trained in the operation of the automated systems. Fox River Stone was shut down for a month while the machinery and automation systems were installed and final testing was completed. It was operational by May 2000. During the down time, Fox River Stone had stockpiled rock and worked with customers to continue to meet their needs.
Also providing support for the start-up of the turnkey operation was Roland Machinery of Bolingbrook, Ill., a Metso Minerals distributor. Lamont Cantrell, general manager for the Chicago division of Roland Machinery, explained that because Metso Minerals designed an entire system, a lot of testing and tweaking occurred, “similar to a shake-down cruise on a ship.” He said his company acts as a communication liaison between Metso Minerals and the quarry.
Fox River Stone supplies crushed dolomite products to asphalt and concrete companies. Fox River Stone is a state-certified quality control/quality assurance (QC/QA) supplier for Illinois DOT projects and meets all Superpave regulations for state and federally funded projects. Fox River Stone employs 14 people in its quarry operation. Because it is located in a growing residential area in South Elgin, it is allowed to operate only 12 hours a day and 10 hours on Saturday.
Fox River Stone is unique in its mining process. The quarry has a contractor remove 68 ft. of soil and clay to expose a 38-ft. depth of mineable rock. This equates to about 150,000 cu. yds. of overburden to be removed monthly, which is used to reclaim mined-out areas. Land that has been mined and filled is planted with native grasses and trees to complete the reclamation process.
A buffer of trees and grasses surrounds Fox River Stone and a high-pressure, dust-suppression system is installed on plant equipment. Water trucks further reduce dust.
The turnkey operation by Metso Minerals is one of the few the company has done in North America. “Metso Minerals has been doing turnkey operations in Europe for almost 40 years,” said Lange.
Crushing equipment includes a Nordberg C3055 jaw primary crusher plant. Six-in.-minus rock then travels to a secondary cone crusher, a Nordberg HP300. It is screened, and if necessary, is processed through one of two tertiary crushers, both Nordberg HP400 cone crushers.
The site of the secondary and tertiary crushers, along with the conveyor belts, is 600 ft. long and 135 ft. wide. The primary crusher is located approximately one-half mile from the secondary plant. The plant layout was designed to most efficiently utilize the area the company has available for processing.

the bottom line...

Rein, Shulz & Dahl’s Fox River Stone Company had installed an automated Metso Minerals turnkey system, and it expects yearly production capability to increase by 36 percent over previous years.

To submit a suggestion for a Success in the Field or for more information about this story, contact AggMan at (717) 337-0027, fax (717) 337-9337 or e-mail Bill@aggman.com.


Maintenance Matters

Battery Battles

Editor’s Note: This monthly column is supplied exclusively for AggMan by The Equipment Maintenance Council (EMC).
As soon as one puts the key in the ignition of a vehicle and it does not start, the immediate reaction is “Battery problem!” But as Roland Best from Best Battery in Baltimore, Md., reports, batteries today do not cause many vehicle problems.

When a vehicle fails to start, the usual suspect is not always to blame.

“The battery manufacturing process is typically very good,” said Best. “Most batteries simply wear out over time. For fleet-wide problems, a qualified electrical technician is sometimes needed to determine the actual cause.”
And Best should know. His service manager, Harold Winterbottom, has been with Best Battery for many years and has made literally hundreds of road calls to solve problems for customers.
Take, for example, the case of one major airline who was experiencing problems with their baggage loaders.
“It was the middle of winter and this airline called us frantically because half of their baggage loaders would not start,” explained Winterbottom. “The equipment spent a great deal of time idling on the runway in harsh winter weather.”
Winterbottom took amp readings at idle and while revving the engine, and it was determined that the battery was not getting enough current at idle. After a period of time, the battery charge would simply run out. Upon reviewing both the airline’s equipment and operating environment, it was decided that a specially designed heavy-duty starter and alternator package was needed to accommodate long idle times on the runway. Best commented that this airline has not had any battery or starter-related problems with baggage loaders to date.
A well-known bakery company was complaining about frequent problems with dead batteries on delivery trucks. Upon investigation of the electrical system, Winterbottom noticed that there was a constant drain on the battery causing it to lose its charge. Warehouse workers frequently played the delivery van’s radio while loading the trucks. The aftermarket radios were wired to the ignition side, instead of the accessory side of the switch, which created an 8-amp draw from the battery. A simple re-wiring solved the bakery’s problem.
Best recommends reviewing persistent battery and starting problems with a qualified electrical technician before making any conclusions about defective equipment. And when batteries do fail (as they sometimes do), Peggy Bykowsky, battery product manager for John Deere explains that they typically fail for one of two reasons:
About 50 percent of batteries fail because of the natural internal corrosion process that builds up after years of use. This corrosion causes the battery to lose its chemical effectiveness, and therefore it can no longer hold a charge. Incidentally, hot weather and high ambient temperatures are linked to early battery failures. Batteries used in very hot climates tend to have shorter useful lives than their counterparts in cooler climates.
The other 50 percent of batteries fail as a result of poor maintenance, improper charging techniques or general abuse. To prolong battery life, Bykowsky suggests the following:

  • Check batteries in the spring and fall for leakage, state-of-charge, loose or frayed wires;
  • Make sure terminal connections are tight and free from corrosion to increase starting capability;
  • Use the proper battery type for the application;
  • Check fluid levels twice a year and do not overfill batteries to avoid leakage that can result in damage to the battery;
  • Keep battery holddowns tight to reduce vibration that can damage cases and plates; and
  • Disconnect the battery ground cable if the equipment will not be used for 60 days or longer. This will help reduce power drainage and prolong battery life.

Roland Best is president of Best Battery. He can be reached for comments or questions at (410) 342-8060. Peggy Bykowski is battery product manager for John Deere. She can be reached for comments or questions at (309) 765-4372.

The Equipment Maintenance Council (EMC) is an individual membership organization comprised of equipment maintenance professionals. Its members are responsible for the purchase, maintenance, employee training, shop facilities and parts management of leading corporations and government entities that utilize heavy, off-road equipment. Its members also represent the major manufacturers and suppliers of the heavy equipment industry. EMC provides end users with cutting-edge education, and it is the only organization to offer a certification program for the industry, the Certified Equipment Manager (CEM). For more information, contact Stan Orr, CAE, EMC executive director,
at (970) 384-0510, e-mail at ceo@equipment.org, or visit EMC’s web site at www.equipment.org.


Winter Battery Storage Tips

Cold temperatures can be particularly detrimental to batteries that must be stored for the winter season. Gale Kimbrough from Interstate Battery System of America, Inc. in Dallas, Texas, recommends taking the following steps for long-term battery storage:

  • Disconnect and remove the battery from the vehicle.
  • Fully charge batteries to 100 percent before storing because they can deteriorate when allowed to remain discharged for extended periods of time. *Note: Always charge batteries according to charger instructions.
  • Store battery in a cool, dry place and avoid areas where excessive heat or cold could affect the battery.
  • Clean the battery case and terminals before storing. Clean with a neutralizing solution and dry thoroughly.
  • Check and correct electrolyte levels before storage. The proper electrolyte fill level is 1/8 in. below the vent well split ring.
    It is best to use distilled or deionized water to fill the level as high as splash barrels (split ring) or as low as plate tops.
  • Do not stack batteries on top of one another.
  • Test the battery’s state-of-charge every six to eight weeks with a hydrometer or voltmeter to verify state-of-charge
    is above 75 percent.
  • Always observe safety precautions when working on or near batteries.

Gale Kimbrough is technical services manager with Interstate Battery System of America, Inc. He can be reached for comment or questions at (800) 541-8419, ext. 6866.

AggMan is a publication of Mercor Media, Inc.
Copyright Š 2001 - Mercor Media, Inc.